This week the construction workers at St. Francis and Clare School did an extraordinary good job in moving the construction site forward. Their hard
work and effort finally shows in various ways. Therefore we are very proud to announce that the following milestones have now been
achieved:
-
The top floor panels in the library wing have all been set
-
Floors have been completed in two classrooms
-
The remaining doorframes have been installed in the ground floor
-
The ramp for wheelchair access has been completed
-
There has been significant progress at the toilets, both for the students and for the staff
-
Septic tank 1 is about to be completed within the next couple of days